Drivers in Hampton Roads can expect closures on water crossings, interstates and notable detours for the week of Nov. 25 to Dec. 1.

This list covers full closures of interstates, ramps, bridges and primary roads, and single lane closures at the bridge-tunnels and the Berkley, High Rise and James River bridges.

For information on the many other lane closures necessary for maintenance and construction throughout Hampton Roads, visit 511Virginia, download the 511 smartphone app, dial 511 or listen to Highway Advisory Radio (HAR) 1680AM.

Bridges

High Rise Bridge, I-64
  • Full stoppages in both directions, Dec. 2, between 4 a.m. and 7 a.m. lasting no longer than 15 minutes. Motorists should expect delays.
George P. Coleman Bridge, Route 17
  • Full stoppages in both directions, Nov. 27-30 between 9 a.m. and 3 p.m. lasting no longer than 20 minutes. Motorists should expect delays.

I-64

Segment II
  • Full ramp closures on I-64 with signed detours in place, on Nov. 26-29, as follows:
    • I-64 east and west to Route 60/Busch Gardens (exit 243A), as early as 7 p.m. to 5 a.m.
    • I-64 east and west to Route 143 (exit 243B), as early as 7 p.m. to 5 a.m.
    • Route 60 on-ramp to I-64 east and west, as early as 7 p.m. to 5 a.m.
    • I-64 east and west to Route 199 west (exit 242A), as early as 7 p.m. to 5 a.m.
    • I-64 east and west to Route 199 east (exit 242B), as early as 7 p.m. to 5 a.m.
    • Route 199 east and west on-ramps to I-64 east and west, as early as 7 p.m. to 5 a.m.
    • I-64 east and west to Yorktown Road/Jefferson Avenue (exit 247), as early as 7 p.m. to 5 a.m.
    • Jefferson Avenue (Route 143) on-ramps to I-64 east and west, as early as 7 p.m. to 5 a.m.
    • Yorktown Road (Route 238) on-ramp to I-64 east, as early as 8 p.m. to 5 a.m.
**Detour signs will be in place. All ramps will not be closed at the same time to maintain access to the detour routes.
Segment III
  • Starting overnight on Nov. 26, westbound traffic shifts will continue on I-64 from the Route 199/Lightfoot (exit 234) to the western limits of the Segment III Project approximately 1 mile west, weather permitting. Traffic will be shifted to the outside lane and shoulder to allow for clearing in the median and construction of the new travel lane.
  • Starting overnight on Nov. 26-29, eastbound traffic shifts will begin on I-64 between the western limits of the Segment III Project, approximately 1 mile west of Route 199/Lightfoot (exit 234) and the Queens Creek bridges (mile marker 239), weather permitting. Traffic will be shifted to the outside lane and shoulder to allow for clearing in the median and construction of the new travel lane.
  • A consecutive, long-term full ramp closure on Route 143 Merrimac Trail north to I-64 west in place. Traffic will follow detour signage in place directing motorists to the Route 143 south on-ramp to I-64 west during the closure.
Hampton Roads Bridge-Tunnel
  • Single-lane closure east
    • Nov. 27-29, 8 p.m. to 5 a.m.
    • Nov. 30, 10 p.m. to 5 a.m.
  • Full Tunnel closure
    • I-64 east, Dec. 2, 2 a.m. to 3 a.m.
    • I-64 west, Dec. 2, 3 a.m. to 4 a.m.

I-264

I-64/I-264 Interchange Improvements
  • I-264 east ramp (exit 15A) to Newtown Road will be closed for up to 15 minutes on Nov. 26-29 between 12:01 a.m. and 4 a.m.

I-664

I-664, Monitor-Merrimac Bridge-Tunnel
  • Single-lane closure north Nov. 26-30, 8 p.m. to 5 a.m.

I-564

I-564, Norfolk
  • I-564 west/east at the Runway Tunnel single-lane closure Nov. 26, 12 p.m. to 5:30 p.m. and Nov. 27-30, 9 a.m. to 5:30 p.m.
  • I-564 west from I-64 to Terminal Blvd. single-lane closure Nov. 26, 12 p.m. to 7 p.m. and Nov. 27-Dec. 1, 9 a.m. to 7 p.m.