Dominion Virginia Power may have to restart the U.S. Army Corps of Engineers permitting process before it can build a power line across the James River, a process that could take nearly two years.
Dominion submitted an application to USACE for its preferred power line route in August, three months before the State Corporation Commission approved of a different variation. A USACE permit is required before Dominion can build a 500kV power line on towers across the James River, and the permit must be issued for the route approved by the SCC.
The power company submitted a request to the SCC in 2012 for a line planned to move power to the Hampton area. Several line variations were planned, but only a few lines were deemed viable due to home and airspace encroachments.
Dominion preferred a route called “Variation 1” that would run from the Surry Nuclear Power Station across the James River, bisecting land owned by BASF Corporation – a chemical company with property in James City County – to end at the planned Skiffes Creek Switching Station. From the switching station, power would be carried on 230kV lines down the Peninsula to Hampton. Dominion submitted an application to USACE based on this route.
BASF objected to the variation Dominion preferred because it would cross an area where the company had been performing work to purge the land of chemical pollution. Instead, BASF supported the Variation 4 route that crossed the northern edge of its property, traversing property owned by the James City County Economic Development Authority and Colonial Williamsburg subsidiary Williamsburg Developments Inc.
James City County opposed an over-river power line altogether, but the SCC approved the over-river line BASF preferred in November.
At a limited hearing Tuesday, Dominion argued for an alternate route approval, again pushing Variation 1 as its first choice because the company has been unable to secure a signed right of way agreement from the county’s EDA. The EDA has passed a resolution to issue a right of way to Dominion five times, each time with the caveat WDI is satisfied with the plan.
Liz Harper, Dominion’s siting and permitting specialist, said the company applied for a permit for Variation 1. If the SCC does not approve that route, the company will likely have to resubmit its application to USACE, restarting the entire public notice, public comment and review process.
USACE has not released any information about the time it needs to issue a decision, but Harper estimated a decision would be announced by May. If the SCC does not approve Variation 1, the USACE decision will not matter.
Whether USACE will require a study on environmental impacts from the line also remains unclear. Dominion has not started a study, which Harper estimated would take about a year to complete. In total, she estimated 21 months would be required to complete a study and obtain USACE approval if the SCC does not approve Variation 1.
SCC Hearing Examiner Alexander Skirpan promised an expedited decision on the James City County piece of the line, but offered no timeline for his decision.
Related Coverage:
- James River Association Joins JCC Appeal on Over-River Power Line
- JCC Supervisors Vote to Appeal SCC Ruling on Dominion Over-River Power Line
- SCC Reopens Over-River Power Line Case, Sets Hearing Date
- SCC Reopens Case on Dominion-Proposed Power Line Over James River
- JCC EDA Won’t Give Dominion OK on Power Line Until Other Owners Agree
- SCC Gives Green Light to Dominion’s Over-the-James Power Line
- JCC Thanks Williamsburg For Help in Fighting Overhead Power Line
- National Park Service Offers Opposition Letter to Dominion’s Proposed Overhead Power Line
- JCC Files Opposition to SCC Hearing Examiner’s Report on Dominion Power Line
- SCC Examiner Recommends Over-the-James River Power Line
- JCC Submits Court Petition to Block Proposed Power Line Over James River
- Closing Briefs Filed in Dominion Overhead Power Line SCC Case
- JCC Denies Site Plan Approval for Dominion’s Skiffes Creek Station; Still No Application Submitted for SUP
- SCC Hearing Concludes for Power Line Case
- JCC Offer to Purchase Land for Dominion Not Rooted in Prior County Discussion
- Power Line Hearing: JCC Offers to Buy Land, Questions Veracity of Dominion Research
- Evidentiary Hearing on Proposed Overhead Powerline to Begin Today
- JCC Supes to Vote on More Funding for Fight Against Dominion
- Officials Unsure Retrofitting Entire Yorktown Power Station is an Option
- SCC Changes Hearing Examiner, Date for Dominion Power Line Case
- GA Subcommittee to Send Letter Opposing Proposed Power Lines
- Chickahominy Chief Says Overland Power Line Would Harm Tribal Grounds
- Is Burying Proposed Power Line Across James an Option?