Overnight Lane Closures on I-64 Resume Monday Night

WYDaily.com is your source for free news and information in Williamsburg, James City & York Counties.

Courtesy of Virginia Department of Transportation
Courtesy of Virginia Department of Transportation

Construction crews working on the Interstate 64 widening will begin at 8 p.m. Monday this week.

The work, which will include single lane closures in both directions between Lee Hall (exit 247) and Jefferson Avenue (exit 255), is scheduled between 8 p.m. and 5 a.m. each night through Friday morning.

The first phase of the widening project – estimated to cost about $122 million – will add one lane and one shoulder in each direction for the 5.6 miles between Jefferson Avenue in Newport News and Route 143 in York County (exit 247).

The first phase is slated for completion in December 2017.

The entire I-64 widening, which will happen in three phases, will stretch to the second Route 199 interchange in York County (exit 234).